Biscayne Landing Team has been VERY busy
(link)

We've spent $16,500,000.
We've poured 13,500 cyds. of concrete.
We've placed 1,140 tons of steel.
We've installed 142,000 concrete masonry units. |
 |
|
We've hung 15,100 sq. ft. of glass and glazing.
Framing is installed on 15 floors and drywall is hung on 7 floors.
Each tower has grown structurally by 12 floors. Tower 1 is on its 22nd
of its 26 floors and Tower 2 is on its 15th of its 26 floors. The
interior finish trades are mobilizing as marble and paint gets
underway. And the Tower 1 structural team is beginning to think about
demobilizing.
Keep your eyes and ears peeled for your invitation to the Very first
Gryphon Construction Topping out Party.
- Michelle Malick, Project Manager |
|