Biscayne Landing Team has been VERY busy (link)
We've spent $16,500,000.
We've poured 13,500 cyds. of concrete.
We've placed 1,140 tons of steel.
We've installed 142,000 concrete masonry units.

We've hung 15,100 sq. ft. of glass and glazing.
Framing is installed on 15 floors and drywall is hung on 7 floors.

Each tower has grown structurally by 12 floors. Tower 1 is on its 22nd of its 26 floors and Tower 2 is on its 15th of its 26 floors. The interior finish trades are mobilizing as marble and paint gets underway. And the Tower 1 structural team is beginning to think about demobilizing.

Keep your eyes and ears peeled for your invitation to the Very first Gryphon Construction Topping out Party.

 - Michelle Malick, Project Manager